Gulf Oil Spill Investigation: Questions BP Chairman Tony Haywood Failed to Answer Directly Addressed BP's Negligence
Waxman Sent Letter Asking that Hayward Address "negligent" Cost-cutting Measures on Deepwater Horizon Rig
Despite the rig crew's obvious ongoing difficulties controlling the well, Waxman charged, BP continued using shortcuts up until the day the rig exploded, despite the well having been characterized early on, in BP's own words, as "a nightmare. BP's management of the well has been characterized as negligent by oil industry experts, out of compliance with standard oil industry best practices, and not in line by the American Petroleum Institute guidelines.
Of course, Hayward has since been removed from day-to-day oversight of the gulf oil spill. The questions and concerns he sidestepped and avoided in his testimony are contained in detailed letter Henry Waxman, citing internal BP documents and emails, sent to Hayward before Hayward's appearance.
The text of the committee's letter follows.
Mr. Tony Hayward
Chief Executive Officer BPPLC
1 St. James's Square London SWI Y 4PD
United Kingdom
Dear Mr. Hayward:
We are looking forward to your testimony before the Subcommittee on Oversight and Investigations on Thursday, June 17, 2010, about the causes of the blowout of the Macondo well and the ongoing oil spill disaster in the Gulf of Mexico.
As you prepare for this testimony, we want to share with you some of the results of the Committee's investigation and advise you of issues you should be prepared to address.
The Committee's investigation is raising serious questions about the decisions made by BP in the days and hours before the explosion on the Deepwater Horizon. On April 15, five days before the explosion, BP's drilling engineer called Macondo a "nightmare well."
In spite of the well's difficulties, BP appears to have made multiple decisions for economic reasons that increased the danger of a catastrophic well failure. In several instances, these decisions appear to violate industry guidelines and were made despite warnings from BP's own personnel and its contractors.
In effect, it appears that BP repeatedly chose risky procedures in order to reduce costs and save time and made minimal efforts to contain the added risk.
At the time of the blowout, the Macondo well was significantly behind schedule. This appears to have created pressure to take shortcuts to speed finishing the well. In particular, the Committee is focusing on five crucial decisions made by BP:
(I) the decision to use a well design with few barriers to gas flow;
(2) the failure to use a sufficient number of "centralizers" to prevent channeling during the cement process;
(3) the failure to run a cement bond log to evaluate the effectiveness of the cement job;
(4) the failure to circulate potentially gas-bearing drilling muds out of the well; and
(5) the failure to secure the wellhead with a lockdown sleeve before allowing pressure on the seal from below.
The common feature of these five decisions is that they posed a trade-off between cost and well safety.
On April 19, one day before the blowout, BP installed the final section of steel tubing in the well. BP had a choice of two primary options: it could lower a full string of "casing" from the top of the wellhead to the bottom of the well, or it could hang a "liner" from the lower end of the casing already in the well and install a "tieback" on top of the liner.
The liner-tieback option would have taken extra time and was more expensive, but it would have been safer because it provided more barriers to the flow of gas up the annular space surrounding these steel tubes.
A BP plan review prepared in mid-April recommended against the full string of casing because it would create "an open annulus to the wellhead" and make the seal assembly at the wellhead the "only barrier" to gas flow if the cement job failed. Despite this and other warnings, BP chose the more risky casing option, apparently because the liner option would have cost $7 to $10 million more and taken longer.
When the final string of casing was installed, one key challenge was making sure the casing ran down the center of the well bore. As the American Petroleum Institute's recommended practices explain, if the casing is not centered, "it is difficult, if not impossible, to displace mud effectively from the narrow side of the annulus," resulting in a faiku cement job.
Halliburton, the contractor hired by BP to cement the well, warned BP that the well could have a "SEVERE gas flow problem" if BP lowered the final string of casing with only six centralizers instead of the 21 recommended by Halliburton. BP rejected Halliburton's advice to use additional centralizers.
In an e-mail on April 16, a BP official involved in the decision explained: "it will take 10 hours to install them . ... I do not like this." Later that day, another official recognized the risks of proceeding with insufficient centralizers but commented: "who cares, it's done, end of story, will probably be fine." BP's mid-April plan review predicted cement failure, stating "Cement simulations indicate it is unlikely to be a successful cement job due to formation breakdown."
Despite this warning and Halliburton's prediction of severe gas flow problems, BP did not run a 9- to 12-hour procedure called a cement bond log to assess the integrity of the cement seal. BP had a crew from Schlumberger on the rig on the morning of April 20 for the purpose of running a cement bond log, but they departed after BP told them their services were not needed.
An independent expert consulted by the Committee called this decision "horribly negligent."
In exploratory operations like the Macondo well, wells are generally filled with weighted mud during the drilling process. The American Petroleum Institute (API) recommends that oil companies fully circulate the drilling mud in the well from the bottom to the top before commencing the cementing process.
Circulating the mud in the Macondo well could have taken as long as 12 hours, but it would have allowed workers on the rig to test the mud for gas influxes, to safely remove any pockets of gas, and to eliminate debris and condition the mud so as to prevent contamination of the cement. BP decided to forego this safety step and conduct only a partial circulation of the drilling mud before the cement job.
Because BP elected to use just a single string of casing, the Macondo well had just two barriers to gas flow up the annular space around the final string of casing: the cement at the bottom of the well and the seal at the wellhead on the sea floor. The decision to use insufficient centralizers created a significant risk that the cement job would channel and fail, while the decision not to run a cement bond log denied BP the opportunity to assess the status of the cement job.
These decisions would appear to make it crucial to ensure the integrity of the seal assembly that was the remaining barrier against an influx of hydrocarbons. Yet, BP did not deploy the casing hanger lockdown sleeve that would have prevented the seal from being blown out from below.
These five questionable decisions by BP are described in more detail below. We ask that you come prepared on Thursday to address the concerns that these decisions raise about BP's actions.
BP started drilling the Macondo well on October 7, 2009, using the Marianas rig. This rig was damaged in Hurricane Ida on November 9, 2009. As a result, BP and the rig operator, Transocean, replaced the Marianas rig with the Deepwater Horizon. Drilling with the Deepwater Horizon started on February 6, 20 IO.
The Deepwater Horizon rig was expensive. Transocean charged BP approximately $500,000 per day to lease the rig, plus contractors' fees. BP targeted drilling the well to take 51 days and cost approximately $96 million.
The Deepwater Horizon was supposed to be drilling at a new location as early as March 8, 20103. In fact, the Macondo well took considerably longer than planned to complete.
By April 20, 2010, the day of the blowout, the rig was 43 days late for its next drilling location, which may have cost BP as much as $21 million in leasing fees alone. It also may have set the context for the series of decisions that BP made in the days and hours before the blowout. According to the terms of the contract, the daily rate would range from $458,000 in March 2008 to $517,000 in September 20.
Well Design Deepwater wells are drilled in sections. The basic process involves drilling through rock, installing and cementing casing to secure the well bore, and then drilling deeper and repeating the process. On April 9, 2010, BP finished drilling the last section of the well. The final section of the well bore extended to a depth of 18,360 feet below sea level, which was 1,192 feet below the casing that had previously been inserted into the we1l4
At this point, BP had to make an important well design decision: how to secure the final 1,192 feet of the well. On June 3, Halliburton's Vice President of Cementing, Tommy Roth, briefed Committee staff about the two primary options available to BP. One option involved hanging a steel tube called a "liner" from a liner hanger on the bottom of the casing already in the well and then inserting another steel liner tube called a "tieback" on top of the liner hanger.
The other option involved running a single string of steel casing from the seafloor all the way to the bottom of the well. Mr. Roth informed the Committee that "Liner/Tieback Casing provides advantage over full string casing with redundant barriers to annular flow."s In the case of a single string of casing, there are just two barriers to the flow of gas up the arullliar space that surrounds the casing: the cement at the bottom of the well and the seal at the wellhead. Mr. Roth told the Committee that in contrast, "Liner/Tieback provides four barriers to annular flow.,,6 They are:
(I) the cement at the bottom of the well,
(2) the hanger seal that attaches the liner to the existing casing in the well,
(3) the cement that secures the tieback on top of the liner, and
(4) the seal at the wellhead.
The liner-tieback option also takes more time to install, requiring several additional days to complete. Internal BP documents indicate that BP was aware of the risks of the single casing approach. An undated "Forward Plan Review" that appears to be from mid-April recommended against the single string of casing because of the risks. According to this document, "Long string of casing ... was the primary option" but a "Liner ... is now the recommended option.")
The document gave four reasons against using a single string of casing, They were:
1.Cement simulations indicate it is unlikely to be a successful cement job due to formation breakdown.
2.Unable to fulfill MMS regulations of 500' of cement above top HC zone
3.Open annulus to the wellhead, with seal assembly as only barrier.
4. Potential need to verify with bond log, and perform remedial cementjob(s)
In contrast, according to the document, there were four advantages to the liner option:
"Less issue with landing it shallow (we can also ream it down),"
"Liner hanger acts as second barrier for HC in arlllulus,"
"Primary cement job has slightly higher chance for successful cement lift,"
"Remedial cement job, if required, easier to justify to be left for later."
Communications between employees of BP confirm they were evaluating these approaches, On April 14, Brian Morel, a BP Drilling Engineer, e-mailed a colleague, Richard Miller, about the options, His e-mail notes: "this has been
Despite the risks, BP chose to install the single string of casing instead of a liner and tieback, applying for an amended permit on April 15. The company's application stated that the full casing string would start at 9 7/8 inches diameter at the top of the well and narrow to 7 inches diameter at the bottom, 12 This application was approved on the same day,13 approach, The third version recommends in favor of the single string of casing and is discussed below.
The decision to run a single string of casing appears to have been made to save time and reduce costs. On March 25, Mr. Morel e-mailed Allison Crane, the Materials Management Coordinator for BP's Gulf of Mexico Deepwater Exploration Unit, that the long casing string "saves a lot of time ... at least 3 days.
On March 30, he e-mailed Sarah Dobbs, the BP Completions Engineer, and Mark Hafle, another BP Drilling Engineer, that "Not running the tieback ... saves a good deal of time/money.
On April IS, BP estimated that using a liner instead of the single string of casing "will add an additional $7 -$10 MM to the completion cost. The same document calls the single string of casing the "best economic case and well integrity case for future completion operations."
Around this time, BP prepared another undated version of its "Forward Plan Review." Notably, this version of the document reaches a different conclusion than the other version, calling the long string of casing "the primary option" and the liner "the contingency option.
18 Like the other version of the plan review, this version acknowledges the risks of a single string of casing, but it now describes the option as the "Best economic case and well integrity case for future completion operations. 19 Centralizers Centralizers are attaclm1ents that go around the casing as it being lowered into the well to keep the casing in the center of the borehole. If the well is not properly centered prior to the cementing process, there is increased risk that channels will form in the cement that allow gas to flow up the annular space around the casing.
API Recommended Practice 65 explains: "If casing is not centralized, it may lay near or against the borehole wall. ... It is difficult, if not impossible, to displace mud effectively from the narrow side of the annulus if casing is poorly centralized. This results in bypassed mud charll1els and inability to achieve zonal isolation.
On April 15, BP informed Halliburton's Account Representative, Jesse Gagliano, that BP was planning to use six centralizers on the final casing string at the Macondo well. Mr. Gagliano spent that day running a computer analysis of a number of cement design scenarios to determine how many centralizers would be necessary to prevent channeling.
With ten centralizers, the modeling resulted in a "MODERATE" gas flow problems" Mr. Gagliano's modeling showed that it would require 21 centralizers to achieve only a "MINOR" gas flow problem.
Mr. Gagliano informed BP of these results and recommended the use of 21 centralizers. After running a model with ten centralizers, Mr. Gagliano e-mailed Brian Morel, BP's drilling engineer, and other BP officials, stating that the model "now shows the cement channeling" and that ''I'm going to run a few scenarios to see if adding more centralizers will help us or not.
Twenty-five minutes later, Mr. Morel e-mailed back: "We have 6 centralizers, we can run them in a row, spread out, or any combination. It's a vertical hole, so hopefully the pipe stays centralized due to gravity. As far as changes, it's too late to get any more product on the rig, our only optiois to rearrange placement of these centralizers.
The following day, April 16, the issue was elevated to John Guide, BP's Well Team Leader, by Gregory Walz, BP's Drilling Engineering Team Leader.
Mr. Walz informed Mr. Guide: "We have located 15 Weatherford centralizers with stop collars ... in Houston and worked things out with the rig to be able to fly them out in the morning."
The decision was made because "we need to honor the modeling to be consistent with our previous decisions to go with the long string.
Mr. Walz explained: "I wanted to make sure that we did not have a repeat of the last Atlantis job with questionable centralizers going into the hole.
Mr. Walz added: "I do not like or want to disrupt your operations . ... I know the planning has been lagging behind the operations and I have to turn that around.
In his response, Mr. Guide raised objections to the use of the additional centralizers, writing: "it will take 10 hrs to install them . ... I do not like this and ... I
Published by Dave Williams
Outdoors writer Dave Williams lives in Arlington, Massachusetts. View profile
- BP Oil Company Displayed "Titanic" MentalityIn the months, days and hours leading up to the oil well explosion in the Gulf of Mexico, BP operated as though they thought that they were accident proof
How Does the Gulf Oil Spill Affect Residents of the Louisiana Coastline?The Coalition to Restore Coastal Louisiana has been giving Louisiana residents a chance to get involved in the BP Gulf oil spill clean-up.- The Future Impact of the Gulf Oil Spill: Part TwoThe Gulf Oil Spill continues to send oil flowing into the waters of the Gulf Of Mexico and the long term environmental impact is anyone's guess.
Did Gulf Oil Spill Cause Massive Tornado in Mississippi?My first reaction to hearing about the massive tornado in Mississippi was that it was an affect of the gulf oil spill. I am far from a scientist but did find supporting evidence...
How Will the 2010 Hurricane Season Affect the Gulf Oil Spill?Because this would be the first time in history that a hurricane crosses over a major oil spill, the impact is not known for certain.
- Congress Grills Tony Hayward
- BP CEO Tony Hayward Places 4th in Yacht Race, Cash Then Dash?
- Louisiana to BP CEO Tony Hayward: We'd like Our Lives Back, Too
- New Billboard Message to BP's Tony Hayward
- BP Oil Spill Update: Tony Hayward- Executive Director & Group Chief Executive BP R...
- Amazing Excerpts of BP CEO Tony Hayward's Congressional Testimony
- President Obama, BP's Hayward Take Time Off from Gulf Coast Oil Disaster




