COMMENTARY | The Nuclear Regulatory Commission has taken the extraordinary step of moving the Fort Calhoun nuclear power plant to a special inspection status, Manual Chapter 0350. Fort Calhoun has been shut down since last April. Flooding by the Missouri River and a small fire that caused a power failure in a cooling system have contributed to the NRC's desire to provide enhanced inspection of the plant during its extended shutdown.
The move was announced by the plant's owner, the Omaha Public Power District, on Tuesday. The Washington Post reports the NRC's inspection revealed plant errors in providing incident warnings to local officials and a defective or improperly installed part that lead to the fire. OPPD states that they have "aggressively and thoroughly" addressed the issues. The change in status will allow the NRC to review process and procedural documentation, plans, maintenance and inspection reports and other material in an in-depth manner without affecting plant operations.
The Fort Calhoun nuclear power plant shut down in April of 2011 for routine refueling. In early June, prior to the plant coming back on line, record flooding of the Missouri River began in the area. The plant was surrounded by flood water but none of the critical areas were flooded. A complex series of berms and other flood control measures kept the reactor building and the building housing spent fuel rods dry. Areas of the plant that were unprotected, or were temporarily flooded, are now dry and have been returned to service.
OPPD spent $15.8 million to replace the electric power that Fort Calhoun would have generated during the flood. The costs of purchased electricity will continue to increase as the plant remains in extended shutdown. An added $28.7 million was spent on flood control measures at all of the OPPD facilities threatened by the Missouri River flood, including Fort Calhoun. The utility hopes that a combination of insurance reimbursements and federal flood assistance will allow recovery of most of these costs.
Plant operators had hoped to have Fort Calhoun in full operation by January. With the new inspection status, it is unclear when the plant will resume electrical production.
Published by Charles Simmins
Charles Simmins is a native Western New Yorker with nearly thirty years of experience at senior level accounting positions in non-profit and for profit organizations. He was a volunteer firefighter, and a vo... View profile
Missouri River Flood: Pet Safety TipsAs the Missouri River flooding continues, curious onlookers flock to the water's edge. During an outing to photograph the flood, I noticed a family allowing their dog to drink f...- Missouri River Basin Filling with FloodingThe Missouri River is the longest river in North America. Though the Army Corps of Engineers has constructed massive flood control projects along its length, this year's exceptional rain and snow pack melt are testing...
- Manager Lied About Safety at Nuclear Plant in Ohio, Federal Court RulesA former manager at an Ohio nuclear power plant was convicted of making false statements to the Nuclear Regulatory Commission concerning the safety measures and condition of nozzles at the Besse-Davis plant.
- 34 New Nuclear Power Plants Could Go Online in the Next Decade21 companies throughout the United Sates are seeking permission and permits to build 34 nuclear power plants, mostly along the eastern seaboard of the United States, from New York to Florida.
First Person: 'Sand Bag Jam' Unites Siouxland in Preparation for FloodingMembers of several Siouxland communities gathered Tuesday at the Long Lines Family Rec Center in Sioux City, Iowa, to fill sandbags in preparation for the impending Missouri Riv...
- Nebraska Nuclear Plant Faces Missouri River Flood Fight
- Alabama Nuclear Plant, Farley, Gets a "Yellow" Card
- Rising Missouri River Overtops Levees in Nebraska, Missouri
- Shopping List to Save a Nuke
- The Arbitrary Rulings of the Nuclear Regulatory Commission
- Nebraska Nuclear Plant in Jeopardy
- Jobs with the Nuclear Regulatory Commission